Skip to content
Raken

Extra Work/Change Order Form

Use this checklist to track and record extra work that is outside of your contract scope.

Question

Response Type

1.

Please provide Potential Change Order number (PCO):

Text Answer

2.

What is the work area?

Text Answer

3.

Requesting Party:

Text Answer

4.

Date of Request:

Text Answer

5.

Reason For Change Order:

Text Answer

6.

What specific activities are required to complete this task?

Text Answer

7.

List materials required and associated quantities:

Text Answer

8.

Which workers logged hours against this task?

Text Answer

9.

What equipment was required to complete this task?

Text Answer

10.

Is the work complete? (Please provide photos.)

Yes No N/A

11.

GC Superintendent Authorization

Signature

Free Download

Download our extra work/change order checklist

Need an easy way to track construction work outside of the contract scope? Fill out the form to download our extra work/change order checklist as an editable PDF. We’ll also email you a copy. Then, work through each checklist item to document the change order in detail.

Download this extra work checklist

interior of building under construction.

What is a change order in construction?

A construction change order is a document describing an adjustment to the original scope of work determined at the start of a project.

Change orders can significantly affect project costs. They typically involve the addition of new work or an updated timeline.

Common change order causes

Any number of issues both preventable and unavoidable may necessitate the need for a change order.

Change orders are needed when:

  • Original estimates were inaccurate

  • There were errors made during the design phase of the project

  • Poor weather or safety concerns delayed tasks

  • Material deliveries are delayed

  • The project owner did not clearly communicate expectations

How to prevent change orders

The best way to prevent change orders in construction is to develop a thorough understanding of your capabilities as a contractor. Detailed field production tracking help project managers plan estimates and draft accurate bids, so your business can avoid change orders—and even worse, disputes or litigation—based on violations of contract terms.

Once project work begins, closely monitor progress onsite to catch potential causes for delays early. Identifying and correcting safety concerns and clearly communicating weather conditions to the project owner can prevent change orders and keep your project on track.

How to track construction change orders in the field

Follow these steps in the field to make sure change orders are processed as smoothly as possible:

  • Number the change order

  • Document the details

  • Specify the reason

  • Log materials and equipment needed

  • Use an extra work/change order checklist

1. Number the change order

When a reason for a change order is identified, create a potential change order number (PCO). This number should be unique and will be used to track the change order as it is completed.

2. Document the change order details

What kind of work is the change order for? Who requested the change order, and when did they request it? What work areas will be affected?

These answers should all be documented with the change order.

3. Specify the reason for the change order

Carefully outline the specific reasons for the change order.

For example, when working on the foundation of a new building a foreman may notice that measurements in the original design blueprints were incorrect after work has begun. The construction crew may need to tear down the work they’ve completed to make corrections, delaying the entire project.

This information should be included in the change order.

Likewise, if a material supplier informs the supply chain manager that a specific tile the project owner requested for flooring will not be available until well beyond the estimated finish date, the construction company should document all communications with the supplier in detail.

4. Log materials, equipment, and labor

Contractors should treat a change order just like any other part of a project.

You need to accurately estimate the time and materials the new work requires, and you’ll need to plan labor and equipment to make sure you have the crew and machinery available onsite you need to complete the change order work as scheduled.

5. Use a change order checklist

Using a change order checklist helps contractors make sure they leave no stone unturned. Instead of remembering all the details offhand, they can use the checklist to verify they have all the information they need to complete the work required by the change order and document it accurately.

Get more checklists in our app

Want checklists your field team can complete on the go? Our mobile construction safety management app app offers an easy-to-use construction checklist library plus toolbox talks, photo and video documentation, and more safety-enhancing features.

construction checklist shown on Raken’s web and mobile app.

We use cookies to manage and improve your website experience.